1. Key takeaways

Article 27 provides the electronic system for the registration of economic operators, and Article 28 requires manufacturers, authorised representatives and importers to submit the information of Section 1 of Part A of Annex VI to that system before placing devices on the market, obtaining a Single Registration Number (SRN) after verification by a competent authority. Article 28(3) states the purpose precisely: the SRN is used when submitting an application for conformity assessment to a notified body and when accessing EUDAMED to fulfil the obligations of Article 26. From 2026-05-28, the first four modules of EUDAMED are mandatory, and the SRN becomes a substantive precondition for non-EU manufacturers: without an activated SRN, conformity assessment applications, device registration and public retrievability of actor data all stall, because every downstream submission in EUDAMED references the actor record as its foreign key.

2. Legal basis

Regulation / documentProvisionDateSource
Regulation (EU) 2017/746 (IVDR)Article 27 (electronic system for registration of economic operators); Article 28(1)–(8) (registration, SRN, updating, confirmation, public availability, fees)Adopted 2017-04-05; applicable 2022-05-26EUR-Lex
Same documentAnnex VI Part A Section 1 (information to be submitted for registration); Article 26 (device registration); Article 30 (EUDAMED)2017-04-05EUR-Lex
Commission Decision (EU) 2025/2371Functional notice for the first four modules2025-11-26; OJEU 2025-11-27EUR-Lex
MDCG 2020-15 / MDCG 2019-5Use of the SRN in Member States / registration of legacy devices in EUDAMED (interpretive)2020 / 2019European Commission

3. Expert insights

Insight 1: One key opens three locks.

Article 28(3) writes the purposes of the SRN clearly: submitting an application for conformity assessment to a notified body, and accessing EUDAMED to fulfil the device registration obligations of Article 26. In addition, Article 29(2)(a) requires the summary of safety and performance to state the SRN, where one has been issued. Without an SRN, three things stall simultaneously: the conformity assessment application, the device registration, and the publication of the actor data. For project planning, this makes the SRN the first milestone of any EU IVD launch, because every downstream dependency — notified body contracting, Annex VI device data submission, the summary of safety and performance — assumes an actor record that a competent authority has verified.

Insight 2: Registration data follow a dual rhythm of updating and confirming.

Article 28(4): information must be updated within 1 week of any change. Article 28(5): within 1 year of submitting the information, and thereafter every 2 years, the accuracy of the data must be confirmed; if the confirmation does not take place within 6 months of the respective deadline, any Member State may take appropriate corrective measures within its territory. Article 28(6) adds that, without prejudice to the responsibility of economic operators for the data, the competent authority shall verify the confirmed data. Companies should treat the two rhythms as separate calendar obligations: the one-week update clock runs on every corporate change (name, address, contact persons), while the one-year and two-year confirmation clocks run on fixed dates from the original submission.

Insight 3: Data publicity and fees are written in the same article.

Article 28(7): the data referred to in paragraph 1 shall be publicly available. Article 28(8): competent authorities may charge manufacturers, authorised representatives or importers in accordance with Article 104. Registration is therefore both an obligation and a publicly retrievable compliance signal: customers, competitors and authorities can see whether an actor record exists, who the verified contacts are and whether the record looks maintained. A stale public record is a reputational and enforcement exposure at the same time, since the corrective-measure mechanism of Article 28(5) can be triggered precisely by unconfirmed data.

Insight 4: From 2026-05-28 there is no Member State substitute route for actor registration.

Under Commission Decision (EU) 2025/2371 (adopted 2025-11-26, published in the OJEU on 2025-11-27) and the gradual roll-out mechanism of (EU) 2024/1860, the first four modules become mandatory from 2026-05-28, and actor registration is among them. Local substitute arrangements previously accepted by some Member States no longer serve as a compliance route (see the dedicated article on the EUDAMED mandatory date in this series). Actors that postponed registration on the assumption that a national workaround would remain available should re-plan immediately, because the verification step by the competent authority adds time that cannot be compressed at the deadline.

4. Practical recommendations

  1. Make the SRN the first milestone of project start-up, ahead of the notified body application and device registration.
  2. Assign an owner for the Annex VI Part A Section 1 information and set calendar reminders for the 1-week updates and the 1-year / 2-year confirmations.
  3. Add a check on whether EUDAMED actor data are synchronised to the change management process.
  4. Confirm whether the Member State concerned charges fees under Article 28(8) together with Article 104, and include them in the annual budget.
  5. Register legacy devices through the EUDAMED-DI route and check the data items against MDCG 2019-5.

5. Verification checklist

  • □ Manufacturer, authorised representative and importer all registered under Article 28 with SRNs obtained
  • □ Annex VI Part A Section 1 information submitted in full and verified by a competent authority
  • □ Mechanism for updates within 1 week of change established (Article 28(4))
  • □ Calendar set for confirmation at 1 year and every 2 years thereafter (Article 28(5))
  • □ Public data scope confirmed (Article 28(7)) together with Member State fees (Articles 28(8) and 104)
  • □ Back-registration route for legacy devices (EUDAMED-DI) confirmed

Legal information verified as of 2026-10-29.

GRZAN supports in vitro diagnostic manufacturers entering the EU market under Regulation (EU) 2017/746 as EU Authorised Representative (EC REP) and PRRC provider, including EUDAMED actor registration and SRN acquisition, Annex VI data preparation, confirmation calendars and fee budgeting. For EUDAMED registration support, contact info@grzanglobal.com.

Disclaimer

Prepared by GRZAN from publicly available regulation. It is provided for general information only and does not constitute legal advice. Legislation and official fees are subject to change by the competent authority.

About GRZAN

GRZAN (Global Regulatory Zone Access Navigator) — the global market-access navigator for medical devices and IVDs.

GRZAN is a specialist consultancy for medical device and IVD market access, providing end-to-end regulatory solutions across the product lifecycle and making international market entry simpler and faster.

Key figures. More than 25 wholly owned subsidiaries worldwide covering 50+ countries and regions; chosen by 100+ listed and leading Chinese device manufacturers, with 4,000+ successful cases; 12+ years in the sector and 200+ regulatory training sessions and seminars delivered.

What we do. Global market access: multi-country registration programmes, technical documentation, regulatory advice. Clinical evidence: clinical evaluation reports (CER), usability studies, overseas clinical investigations. Quality systems: ISO 13485, MDSAP, FDA QMSR and BGMP implementation and audit readiness. Authorised representative and licence-holder services across Southeast Asia, Latin America, the Middle East, Africa, Europe and North America.

Why GRZAN. A real operating entity, with the certificate held by the manufacturer: our direct overseas subsidiaries act as the compliant local holder, so the regulatory relationship stays clear and you keep control rather than being tied to a distributor. Direct access to the team: no time-zone gap, no language barrier, no cultural gap. Review points anticipated: we know what FDA 510(k), EU MDR, Southeast Asian, Latin American and Middle Eastern reviewers look for, which shortens timelines and reduces deficiency letters. Pathway planning: pre-decision analysis and risk assessment before you commit.

Every engagement rests on three commitments: efficiency through pre-submission review, certainty through a clear pathway, and stability through a licence-holder that stays in place.

Take your devices global with GRZAN

We work with manufacturers worldwide to open new markets with a clear regulatory pathway.

Contact us
WhatsApp
QR Code
WhatsApp QR Code
Scan to chat on WhatsApp
Phone
Call
Office Mon-Fri 9:00-18:00
0755-88659477
Mobile 24/7 Service
+86 15816864648
Email
Mail