Registration Approval Timelines of 70 and 100 Working Days

Updated: 2026-11-11 · GRZAN Regulatory Team · Verification date 2026-10-20

1. Key takeaways

Article 17 of the Implementing Rules is the core provision on scheduling: the decision on a registration application should be made within a period counted from the date on which the application and the information required for approval are complete — 70 working days for Class IIb devices and 100 working days for Class III devices; owing to the degree of complexity or other reasonable grounds, the Director of ISAF may extend the period by up to 45 working days as an exception, and shall notify the applicant before the expiry of the original period. The key mechanism is the suspension of the count: when ISAF requests the submission of further information or notifies the correction of deficiencies, the period is suspended from the date of the notification until the date on which the submission or correction is completed.

  • The 70 and 100 working-day periods run from the date the dossier is complete, not from the date of submission.
  • The suspension mechanism has no upper limit and is the main source of schedule overruns.
  • Any extension must be notified before the original period expires, giving the applicant a predictable checkpoint.
  • Changes to registration information requiring prior approval carry a separate period of up to 100 working days, extendable by 45 working days.
  • Patent-protected devices under Article 15 sit outside the general approval period and must be scheduled separately.

2. Legal basis

The approval periods, extensions and suspension mechanism for registration are governed by the following instruments, verified as of 29 October 2026.

RegulationReferencePublicationProvisions
Implementing Rules of the Medical Device Supervision SystemAdministrative Regulation No. 11/2026 (Issue No. 20/2026 of the Official Gazette)Published on 18 May 2026; in force on 1 July 2026Article 13 (review of registration, formal review of 20 working days); Article 17 (approval period for registration); Article 19 (decision period for changes to registration information)
Medical Device Supervision SystemLaw No. 12/2025 (Issue No. 30/2025 of the Official Gazette)Published on 28 July 2025; in force on 1 July 2026Article 15 (patent-protected medical devices, excluded from the application of Article 17(1))
Pharmaceutical Administration Bureau service information for first-time applicationsPublished on the government portalCurrent version, verified as of 2026-10-29Processing instructions for first-time applications

3. Expert insights

Insight 1: the 70 and 100 working days run from the point at which the dossier is complete, not from the point of submission. The starting point under Article 17(1) is the day on which the application and the information required for approval are complete. Before that point, there is still the 20-working-day formal review under Article 13. Adding the two segments together, the best-case schedule is approximately 90 working days for Class IIb and approximately 120 working days for Class III (a practical estimate, excluding correction and inspection time).

Insight 2: the suspension clause is the main source of schedule overruns. Article 17(3) lists two suspension scenarios: (1) a request under Article 10(5) for the submission of further information; and (2) a notice under Article 13(5) to correct deficiencies. The suspension period has no upper limit — which means that in theory the approval can remain pending indefinitely. The only way to control the actual cycle is to complete the dossier in one pass. Every request for further information or notice of correction restarts the clock only after the applicant has responded, so the elapsed time between the two dates is entirely within the applicant’s own control.

Insight 3: an extension must be notified before the original period expires. Article 17(2) requires the Director of ISAF, when extending, to notify the applicant before the expiry of the original period. This gives the applicant a predictable checkpoint: if no extension notice has been received before the 70th working day (for Class IIb), the approval period has already expired.

Insight 4: the decision period for changes to registration information is longer. Article 19(5) provides that for changes to registration information requiring prior approval, ISAF shall make a decision within up to 100 working days from the date on which the information is complete, and the period may likewise be extended by 45 working days. The time cost of a major change can approach that of a full registration.

Insight 5: Article 15 (patent-protected medical devices) is excluded from the application of Article 17(1). For devices involving patents, the general approval period of Article 17(1) does not apply, and scheduling must be assessed separately.

4. Practical recommendations

  • Build a dossier-complete-date ledger: treat the date on which ISAF confirms that the dossier is complete as the scheduling start point, not the submission date.
  • Treat deficiency corrections as project risk: every correction suspends the running of the period, so an internal review should be completed before the first submission.
  • Use the 70th and 100th working days as monitoring checkpoints: if no extension notice has been received by the deadline, proactively query ISAF on progress.
  • Schedule major changes at 100 working days: do not treat a change as a fast-track process.
  • Reserve separate time for patent-related products: the general approval period does not apply in the situations of Article 15.

5. Verification checklist

  • □ It has been confirmed whether the product falls under 70 working days (Class IIb) or 100 working days (Class III)
  • □ The 20-working-day formal review has been included in the overall schedule
  • □ The two suspension scenarios of Article 17(3) have been identified and entered into the risk register
  • □ Monitoring and query mechanisms for the 70th and 100th working-day checkpoints have been set up
  • □ Major changes have been scheduled at up to 100 working days
  • □ The approval period for patent-related products has been assessed separately

Regulatory information verified as of 29 October 2026. The regulations, guidelines and effective dates described in this article are limited to the content published by the official sources listed under Legal basis as of that date; where official documents are subsequently updated, the latest published version prevails.

How GRZAN can help. GRZAN provides medical device and IVD registration, quality system, authorised representative and local testing support for Macao, China. Our team manages Health Bureau (SSM) pre-market registration and notification applications, prepares reference-approval dossiers, and supports post-market vigilance obligations. Business enquiries: info@grzanglobal.com

Disclaimer

Prepared by GRZAN from publicly available regulation. It is provided for general information only and does not constitute legal advice. Legislation and official fees are subject to change by the competent authority.

About GRZAN

GRZAN (Global Regulatory Zone Access Navigator) — the global market-access navigator for medical devices and IVDs.

GRZAN is a specialist consultancy for medical device and IVD market access, providing end-to-end regulatory solutions across the product lifecycle and making international market entry simpler and faster.

Key figures. More than 25 wholly owned subsidiaries worldwide covering 50+ countries and regions; chosen by 100+ listed and leading Chinese device manufacturers, with 4,000+ successful cases; 12+ years in the sector and 200+ regulatory training sessions and seminars delivered.

What we do. Global market access: multi-country registration programmes, technical documentation, regulatory advice. Clinical evidence: clinical evaluation reports (CER), usability studies, overseas clinical investigations. Quality systems: ISO 13485, MDSAP, FDA QMSR and BGMP implementation and audit readiness. Authorised representative and licence-holder services across Southeast Asia, Latin America, the Middle East, Africa, Europe and North America.

Why GRZAN. A real operating entity, with the certificate held by the manufacturer: our direct overseas subsidiaries act as the compliant local holder, so the regulatory relationship stays clear and you keep control rather than being tied to a distributor. Direct access to the team: no time-zone gap, no language barrier, no cultural gap. Review points anticipated: we know what FDA 510(k), EU MDR, Southeast Asian, Latin American and Middle Eastern reviewers look for, which shortens timelines and reduces deficiency letters. Pathway planning: pre-decision analysis and risk assessment before you commit.

Every engagement rests on three commitments: efficiency through pre-submission review, certainty through a clear pathway, and stability through a licence-holder that stays in place.

Take your devices global with GRZAN

We work with manufacturers worldwide to open new markets with a clear regulatory pathway.

Contact us
WhatsApp
QR Code
WhatsApp QR Code
Scan to chat on WhatsApp
Phone
Call
Office Mon-Fri 9:00-18:00
0755-88659477
Mobile 24/7 Service
+86 15816864648
Email
Mail